hide informationshow information

Validation Resources

Our team were contacted to deploy three C&Q resources within one week, to manage the C&Q elements of mechanical tie-ins over a six month period on behalf of the client. This involved working on 30 indirect impact systems, development of associated protocols, walking down systems, capturing punch items, verifying drawings and that the mechanical and electrical contractors were building as per client’s requirements. This led to the successful turnover of these systems as well as a significant pump change out on the process water system serving the entire site.

  • Clients: MSD, Carlow
  • Completion: May 2020 - 6 months
  • Project Type: Validation Protocol & Report Generation
  • Cost: €175,000